Why does plaster take so much longer to dry than drywall?
Because there is more material and more layers holding the water. A plaster wall is a thick mass over wood lath with a cavity behind it, and each layer releases moisture at its own rate. Drywall is thin and either dries quickly or is cut out; plaster is dried through the assembly over days.
The assembly works against quick drying in every respect. The plaster mass itself stores water, the keys behind the lath store more, and the wood lath swells and holds it in a way gypsum board never does. None of those three is reachable from the room side without opening the wall, which is the thing the drying is trying to avoid.
This is why the drying equipment stays longer on an old house than a homeowner expects, and why a surface that feels dry to a hand means very little. Readings taken behind the plaster and in the lath are the only honest measure, and the equipment comes out when those readings match dry plaster elsewhere in the building.
Should wet plaster be cut out or dried in place?
Dried in place wherever the plaster is still sound and keyed to the lath. The test is structural rather than cosmetic: plaster that has detached, crumbled or lost its keys comes down, and plaster that is merely wet stays and gets dried. That judgment is the opposite of the standard approach with drywall.
Plaster that is wet but intact is worth keeping. It is thick, it is original to the building, and replacing it well is skilled work that is hard to match. A restoration approach borrowed from new construction, where everything wet gets cut back to the studs, strips a nineteenth-century house of a surface that could have been saved.
The exception is where safety decides it. A plaster ceiling holding water on keys that have softened is a weight hanging over a room, and the right answer there is controlled removal rather than hoping. A technician will say which of the two situations is in front of you, and why, rather than applying one rule to both.
What makes plaster drying cost more or less here?
The area affected, whether it is a wall or a ceiling, how long the water sat, whether the plaster is over lath or masonry, how much has to be removed on safety grounds, and how long the equipment has to run. No figure appears on this page; the price is set and confirmed by the company taking your call before work starts.
The drivers are mostly about time and access. Plaster takes longer than drywall, so equipment periods are longer, and a wall that can only be reached by opening the cavity from one side is slower than one accessible from both. Ceilings are more labor than walls because overhead work with falling material needs protection and containment.
The age of the building is a real factor rather than a figure of speech. An old house with plaster over lath, a stone cellar, previous patching and no vapor barrier in any assembly gives water more places to be, and all of them have to be found. Severity is assessed on site, and the price is explained and approved before work begins.
Will drying plaster cause mold inside the wall?
Drying is what prevents it; leaving the assembly wet is what does not. Massachusetts does not require a license to conduct mold remediation, according to the Department of Public Health's homeowner guide, but that says nothing about whether the work is needed. The decision rests on readings and on what is found behind the plaster.
The relevant point for a reader is that the cavity behind plaster is dark, still and often insulated, and material left wet in it stays wet for a long time. Getting dry air into that space is the entire purpose of cavity drying, and it is also why surface drying alone is not a solution.
The states in this coverage area handle mold work differently and a reader should know which applies to them. The New York State Department of Labor's Mold Program enforces Labor Law Article 32, which sets licensing and minimum work standards for mold assessors and remediators, and the Department runs a search tool for licensed mold contractors. Connecticut's Department of Public Health says the state does not license or certify mold abatement contractors and that its mold guidelines are guidelines rather than enforceable regulations, while the Department of Consumer Protection says mold remediation on residential property falls under home improvement registration.
When can the wall be repainted or skimmed?
Only after the plaster, lath and framing read dry against a reference reading elsewhere in the house. Paint or a skim coat over damp plaster traps the remaining moisture, bonds poorly and tends to blister or crack within a season, which turns one repair into two.
Finish work is the last step for a reason that is easy to see once it is explained: a coating is a barrier, and a barrier over wet material stops it drying through the face. The old plaster is the part that has to be dry, not the new skim.
Winter adds a complication worth planning around. A house heated hard through a January where lows sit in the low teens Fahrenheit has very dry indoor air, which speeds the drying but also means a wall can read dry at the surface while the cavity lags. That gap is exactly what logged readings at depth are there to catch.